National Green Hydrogen Mission: targets, incentives and opportunities for foreign firms
India wants to become a major producer and exporter of green hydrogen and ammonia, and its National Green Hydrogen Mission has already awarded incentives for 3 GW of electrolyser manufacturing and 862,000 tonnes a year of green hydrogen production. This guide sets out the targets, the money, the auction results and where foreign technology companies, investors and buyers fit, including where the programme is running behind.
By UBR Infra · Updated 28 October 2026 · 32 sources
The mission at a glance
The Union Cabinet approved the National Green Hydrogen Mission on 4 January 2023 with an outlay of ₹19,744 crore: ₹17,490 crore for the SIGHT incentive programme, ₹1,466 crore for pilot projects, ₹400 crore for research and ₹388 crore for other components.[1][2]
The 2030 targets are at least 5 million tonnes of green hydrogen a year, about 125 GW of associated renewable capacity, over ₹8 lakh crore of investment and around 50 million tonnes a year of avoided emissions.[2] The government has said India would need 60–100 GW of electrolysers to get there.[3]
Timelines are slipping. In November 2025 the Secretary of the Ministry of New and Renewable Energy said India would likely reach about 3 million tonnes by 2030 and 5 million tonnes by 2032.[23]
SIGHT incentives: who has won what
SIGHT (Strategic Interventions for Green Hydrogen Transition) pays incentives for electrolyser manufacturing and for green hydrogen production. Electrolyser incentives start at ₹4,440 per kW in year one and fall to ₹1,480 per kW by year five; production incentives were capped at ₹50, ₹40 and ₹30 per kg over the first three years.[4]
| Tranche | Size | Winners include |
|---|---|---|
| Electrolyser manufacturing, tranche I (2024) | 1,500 MW | Reliance, John Cockerill Greenko and L&T (300 MW each), Adani, Ohmium, Homihydrogen, Advait, Matrix Gensol[5] |
| Electrolyser manufacturing, tranche II (2024) | 1,500 MW | Waaree, Matrix, Newage, Advait, Ohmium, Adani[5] |
| Green hydrogen production, tranche I (2024) | 412,000 t/yr | Reliance, ACME and Greenko (90,000 t each), HHP Two[5] |
| Green hydrogen production, tranche II (2025) | 450,000 t/yr | AM Green, Green Infra, L&T and Waaree (90,000 t each), Reliance[5] |
The incentives in detail
| Component | Incentive |
|---|---|
| Electrolyser manufacturing | ₹4,440 per kW in year 1, tapering to ₹1,480 per kW in year 5[4] |
| Green hydrogen production (Mode 1) | Capped at ₹50 per kg in year 1, ₹40 in year 2 and ₹30 in year 3[4] |
| Green ammonia supply (Mode 2A, SECI auctions) | ₹8.82, ₹7.06 and ₹5.30 per kg over years 1–3[5] |
| Transmission | Inter-state charges waived for 25 years for projects commissioned by 2030[10] |
The ammonia auctions show how these combine with buyer demand. The first auction, for Paradeep Phosphates, cleared at ₹55.75 per kg for 75,000 tonnes a year; Jakson Green won Coromandel’s Kakinada volume at ₹50.75 per kg; and the volume-weighted average across all 13 auctions was about ₹53 per kg.[5][6]
Green ammonia auctions: the first real prices
In July and August 2025, SECI ran 13 auctions for 724,000 tonnes a year of green ammonia for fertiliser makers on 10-year contracts. Prices ranged from ₹49.75 to ₹64.74 per kg; ACME won about half the volume, including the lowest bid of ₹49.75 per kg for IFFCO’s Paradeep plant.[5][6] Supply agreements were being signed by March 2026; one buyer’s stock-exchange filing describes a 70,000 tonne-a-year, 10-year contract at price parity with grey ammonia.[7]
For foreign firms these auctions matter twice: they create firm demand for electrolysers, balance-of-plant equipment and EPC services in India, and they set a price benchmark for Indian green ammonia exports.
Refinery demand: the Panipat benchmark
Refineries are the other early buyer. In May 2025 Indian Oil awarded L&T Green a 25-year build-own-operate contract to supply 10,000 tonnes a year of green hydrogen to its Panipat refinery at ₹397 per kg, about US$4.6.[32] It was India’s first end-user offtake auction for green hydrogen and gives bidders a reference price for future refinery tenders.
The structure is worth noting for foreign technology suppliers: the refinery buys hydrogen, not a plant. The developer owns the electrolysers, renewable power and storage, so equipment makers sell to the developer and its EPC contractor rather than to the oil company.
Hubs, standards and incentives
- Hubs. Deendayal (Kandla), V.O. Chidambaranar (Tuticorin) and Paradip ports are recognised green hydrogen hubs.[8]
- Definition. Hydrogen counts as green in India only if well-to-gate emissions are no more than 2 kg of CO2-equivalent per kg of hydrogen, averaged over 12 months.[9]
- Certification. A national certification scheme issued in April 2025 makes facility and annual certificates mandatory, verified by agencies accredited by the Bureau of Energy Efficiency.[9]
- Transmission charges. Inter-state transmission charges are waived for 25 years for green hydrogen and ammonia projects commissioned by 31 December 2030.[10]
- State policies. Andhra Pradesh and Maharashtra offer dedicated incentives such as tax reimbursement, electricity duty and stamp duty exemptions; Gujarat, Tamil Nadu and Odisha support projects through wider industrial policies.[11][12][13]
What counts as green hydrogen in India
India’s Green Hydrogen Standard, notified by the renewable energy ministry in August 2023, sets the bar at no more than 2 kg of carbon dioxide equivalent per kg of hydrogen, measured well-to-gate and averaged over the previous 12 months.[28] The boundary covers water treatment, electrolysis, gas purification, drying and compression, and the definition includes both electrolysis and biomass routes.[28]
The Bureau of Energy Efficiency accredits the agencies that monitor, verify and certify production.[28] The Green Hydrogen Certification Scheme of India, published in April 2025, sets out how producers measure and report emissions and how BEE-accredited verifiers check them.[29]
For exporters this matters because buyers in Europe and Japan apply their own rules. A project certified in India may still need separate certification to sell into the EU or to qualify for Japanese support, so the plant design and power sourcing should be checked against the target market’s rules from the start.
State incentives compared
| State | Policy | Main incentives |
|---|---|---|
| Andhra Pradesh | Green hydrogen and ammonia policy, 2023 | Targets of 0.5 million tonnes of hydrogen and 2 million tonnes of ammonia a year; 100% net state GST reimbursement for five years; electricity duty waived for five years; transmission and cross-subsidy charges reimbursed[11] |
| Maharashtra | Green hydrogen policy, 2023 | Electricity duty exemption for 10–15 years; 50–60% intra-state transmission charge exemption; stamp duty exemption; ₹50 per kg blending subsidy[12] |
| Odisha | Industrial Policy Resolution 2022 | Electricity duty exemption; ₹3 per unit tariff reimbursement for 20 years[27] |
| Gujarat | No dedicated policy | Support through industrial schemes; land on 40-year lease[27][13] |
| Tamil Nadu | No dedicated policy | Mainly non-financial support, including hubs and land[27][13] |
Port hubs and where projects are clustering
In October 2025 the renewable energy ministry recognised three major ports as green hydrogen hubs: Deendayal (Kandla) in Gujarat, V.O. Chidambaranar (Tuticorin) in Tamil Nadu and Paradip in Odisha.[30][31] Hub status brings no direct grant, but projects there can combine central and state incentives with port land and shared infrastructure.[30]
| Hub | What is in place or planned |
|---|---|
| Deendayal, Gujarat | 3,400 acres set aside for green hydrogen and ammonia; a 1 MW electrolyser plant commissioned; a 3.5 million-tonne jetty able to handle green ammonia; a green methanol bunkering facility[30] |
| V.O. Chidambaranar, Tamil Nadu | 205.72 acres allocated; a pilot plant running since September 2025; a green methanol bunkering facility under the mission’s shipping pilot[30][31] |
| Paradip, Odisha | A ₹797 crore jetty for up to 4 million tonnes a year of green hydrogen, ammonia and other liquids, approved in February 2026 as a build-operate-transfer PPP with 20% capital support from the port[30] |
Beyond the ports, the ministry endorsed NTPC’s proposed hub at Pudimadaka in Andhra Pradesh, and five transport pilots were sanctioned covering 37 hydrogen vehicles and nine refuelling stations on ten routes.[31] The Paradip jetty is a direct PPP opportunity for port operators and EPC contractors; the hubs as a whole are where suppliers of storage, handling and safety equipment should focus.
Where foreign firms already play
- Electrolyser technology. Belgium’s John Cockerill formed a 2 GW electrolyser factory venture with Greenko, which won 300 MW of SIGHT capacity; US-based Ohmium built a PEM electrolyser gigafactory near Bengaluru; Germany’s thyssenkrupp nucera partnered BHEL in 2026 to manufacture alkaline electrolysers in India.[14][15][16][5]
- Equity. Petronas’s Gentari agreed to invest US$1.6 billion for 30% of AM Green’s ammonia business.[18]
- Offtake. Germany’s Uniper signed for up to 500,000 tonnes a year of renewable ammonia from AM Green’s Kakinada plant, and AM Green won the Asian lot of Germany’s H2Global tender in 2026. Sembcorp agreed to supply green ammonia from Tuticorin to Japanese buyers.[19][20][17]
- Government partnerships. Japan and India signed a joint declaration on clean hydrogen and ammonia in August 2025, and Germany and India published a joint green hydrogen roadmap in October 2024.[21][22]
The pattern for foreign technology companies is local manufacturing or licensing with an Indian partner, because incentives and procurement preference reward local production. Our partner search service finds and checks that partner; our energy sector brief covers the wider energy transition.
Routes in for foreign companies
| If you are | The usual route | Example |
|---|---|---|
| An electrolyser maker | Local manufacturing through a joint venture, licence or own factory, to qualify for incentives and procurement preference | John Cockerill with Greenko; Ohmium’s own plant; thyssenkrupp nucera with BHEL[14][16][15] |
| A supplier of compressors, storage, safety or balance-of-plant equipment | Supply to the developers and EPC contractors that won SIGHT and SECI awards | Award winners include Reliance, ACME, Greenko, AM Green, L&T and Waaree[5] |
| An investor | Equity in an Indian developer or project platform | Gentari’s 30% stake in AM Green’s ammonia business[18] |
| A buyer of green molecules | Long-term offtake from Indian export projects | Uniper and H2Global with AM Green; Japanese buyers with Sembcorp[19][20][17] |
What is holding the programme back
- Cost. A 2025 Indian Oil tender for green hydrogen at its Panipat refinery cleared at about ₹397 per kg, after two earlier attempts drew weak interest.[24]
- Offtake and payment security. Analysts in late 2025 flagged slow offtake agreements, unclear payment security if buyers default, delayed tenders and lagging transmission.[25]
- Deadlines. The 2030 target has been publicly pushed towards 2032.[23]
For foreign firms, that means picking projects with signed offtake and strong sponsors, and structuring payment security before committing equipment or capital.
Deadlines to watch
- Factories under electrolyser tranche I were due by 9 August 2026, and under tranche II by 26 March 2027.[5] In 2025 manufacturers asked to move the first deadline to 2027 because demand was slow.[26]
- Production under hydrogen tranche I is due by February 2027 and under tranche II by February 2028.[5]
- Analysts expect most projects with 2027 deadlines to miss them.[25]
Delays create openings as well as risk: projects that are behind schedule need equipment, engineering and capital, and some sponsors will look for partners or sellers.
Frequently asked questions
What is the National Green Hydrogen Mission?
India’s national programme, approved in January 2023 with ₹19,744 crore, to build a green hydrogen industry: at least 5 million tonnes a year of production by 2030, electrolyser manufacturing, pilot projects, hubs and standards.
What is the SIGHT scheme?
Strategic Interventions for Green Hydrogen Transition, the mission’s main incentive programme (₹17,490 crore). It pays per-kW incentives to electrolyser manufacturers and per-kg incentives to green hydrogen and ammonia producers, awarded through SECI tenders.
What price did India’s green ammonia auctions reach?
SECI’s 2025 auctions for 724,000 tonnes a year cleared between ₹49.75 and ₹64.74 per kg on 10-year contracts.
What counts as green hydrogen in India?
Hydrogen with well-to-gate emissions of no more than 2 kg CO2-equivalent per kg of hydrogen, averaged over 12 months, certified under India’s green hydrogen certification scheme.
Is India on track for 5 million tonnes by 2030?
Officials said in November 2025 that India was likely to reach about 3 million tonnes by 2030 and 5 million tonnes by 2032.
How can a foreign company take part?
As an electrolyser or technology partner (often through local manufacturing with an Indian company), as an EPC or equipment supplier to awarded projects, as an equity investor in Indian developers, or as an offtaker of green ammonia.
Related
Sources
- Cabinet approves National Green Hydrogen Mission (narendramodi.in)
- The Week, Cabinet approves ₹19,744 crore National Green Hydrogen Mission, January 2023
- pv magazine India, India needs 60–100 GW of electrolysis capacity, August 2023
- Power Line, MNRE's incentives for electrolysers and hydrogen production, August 2023
- SECI, National Green Hydrogen Mission tenders and results
- Renewable Watch, green ammonia auctions, September 2025
- Krishana Phoschem, stock exchange disclosure on green ammonia supply, March 2026
- The Week, three major ports are green hydrogen hubs, October 2025
- AZB & Partners, Green Hydrogen Certification Scheme of India
- Mercom India, ISTS charges waived for green hydrogen and ammonia, May 2023
- Renewable Watch, Andhra Pradesh green hydrogen policy, June 2023
- Renewable Watch, green hydrogen plans in Kerala and Maharashtra, October 2024
- CEEW, Augmenting the National Green Hydrogen Mission, 2025
- Indian Chemical News, Greenko partners John Cockerill, April 2022
- Renewable Watch, BHEL and thyssenkrupp nucera India partner, July 2026
- Renewable Watch, Ohmium electrolyser gigafactory near Bengaluru, July 2024
- H2 View, Sembcorp green ammonia to Japan
- Business Today Malaysia, GIC and Petronas to invest US$1.6 billion in AM Green, October 2023
- Uniper, long-term offtake agreement with AM Green, January 2026
- Argus, AM Green wins H2Global Asia ammonia contract, September 2026
- METI, Japan–India joint declaration on clean hydrogen and ammonia, August 2025
- pv magazine India, India and Germany release green hydrogen roadmap, October 2024
- The Week (PTI), green hydrogen target may slip, November 2025
- NGHM (Economic Times), IOCL Panipat green hydrogen tender, May 2025
- Argus, critical year ahead for India's hydrogen plans, December 2025
- NewsBytes, electrolyser makers seek deadline extension, September 2025
- States leading India's green hydrogen future, July 2025
- Powerline, India announces definition of green hydrogen, August 2023
- Renewable Watch, Green Hydrogen Certification Scheme of India, April 2025
- Indian Infrastructure, Indian ports emerge as green hydrogen hubs, May 2026
- NGHM, PIB release on mission progress, December 2025
- JMK Research, IOCL concludes India's first green hydrogen offtake auction, May 2025
Talk to a partner about India