PPP in India: models, pipeline and how foreign firms take part

India has one of the world’s largest public-private partnership markets, and in January 2026 the government published a pipeline of 852 PPP projects worth more than ₹17 lakh crore. This guide explains how Indian PPPs work, which models are in use today with real examples, where the risks lie, and how foreign contractors, operators and investors take part.

By UBR Infra · Updated 28 October 2026 · 28 sources

Why PPP matters in India now

Three announcements in 2026 set the scale. In January, the Finance Ministry released a three-year pipeline of 852 PPP projects worth more than ₹17 lakh crore: 232 central projects worth ₹13.15 lakh crore (led by roads, power and railways) and 620 state projects worth ₹3.84 lakh crore.[16][17] In February, the government and NITI Aayog launched the second National Monetisation Pipeline for FY2026–30, valued at about ₹16.72 lakh crore across 12 sectors, with highways, power, ports and railways the largest.[5] And the 2026-27 Budget proposed an infrastructure risk guarantee fund to give lenders partial credit guarantees during construction.[18]

India has long been one of the largest PPP markets among developing countries: by World Bank data, 1,265 Indian private infrastructure projects reached financial close between 1990 and 2022, worth about US$296 billion.[19] In 2023 alone, India attracted US$7.0 billion of private infrastructure investment across 27 projects, the fourth-highest in the world.[20]

India’s PPP track record

  • National Infrastructure Pipeline. The 2020–25 pipeline planned ₹111 lakh crore of investment, led by energy (24%), roads (18%), urban (17%) and railways (12%), with the private sector expected to fund 21%.[24]
  • Asset monetisation. The first National Monetisation Pipeline (FY2022–25) raised about ₹5.3 lakh crore, roughly 89% of its ₹6 lakh crore goal.[5][25]
  • Few failures by number. Of India’s private infrastructure projects since 1990, about 3% (5% by investment) were cancelled, according to World Bank data compiled by ADB.[19]
  • But volatile volumes. Private investment in Indian roads fell from US$6.3 billion in 2022 to US$0.91 billion in 2023,[20] and national highway awards fell from 6,300 km in FY2021-22 to about 4,000 km in FY2024-25.[26]

Who runs PPP in India

  • Public Private Partnership Appraisal Committee (PPPAC). Chaired by the Secretary of the Department of Economic Affairs, it appraises central PPP projects above set value thresholds (₹250 crore under its original notification, ₹500 crore for national highways).[4]
  • Viability Gap Funding (VGF). Central grant support for PPPs that are economically justified but not commercially viable. Social-sector projects (water, wastewater, solid waste, health, education) can receive up to 30% of project cost from the Centre and up to 30% from the state; pilot health and education projects up to 40% plus 40%, with operating support; other sectors up to 20% plus 20%.[1][2]
  • India Infrastructure Project Development Fund (IIPDF). Funds transaction advisers to prepare PPP projects, up to ₹5 crore per proposal.[3]
  • Sponsoring authorities. Ministries, state agencies, ports, the National Highways Authority of India (NHAI), Airports Authority of India and city bodies run the actual tenders and sign concessions.

PPP models in use, with current examples

ModelHow it worksCurrent example
BOT-TollThe private partner builds, finances and operates a road and collects tolls, carrying traffic risk.MoRTH revised the BOT-Toll model concession in August 2026, adding revenue support if traffic falls more than 10% short in the early years.[6]
Hybrid Annuity Model (HAM)About 40% of cost paid during construction, the rest as annuities over the operating period; no traffic risk.Namami Gange sewage plants, such as the 165 MLD Howrah–Bally–Baranagar package awarded to VA Tech Wabag with 15 years of operation.[8] See our Hybrid Annuity Model guide.
Toll-Operate-Transfer (TOT)An investor pays an upfront sum for the right to toll and maintain an operating road.NHAI’s TOT Bundle 18 went to IRB for ₹3,087 crore for a 20-year concession (March 2026).[7]
Infrastructure investment trusts (InvITs)Operating assets are sold to a listed or private trust that raises long-term capital.NHAI’s InvIT Round 5 raised ₹6,367 crore for 310 km; NHAI monetised ₹28,307 crore in FY2025-26.[7]
Airport leasesLong-term lease to operate, maintain and develop airports.Six airports were leased to Adani for 50 years; 11 more in five bundles were proposed in 2026.[9][10]
Port terminal concessionsPrivate operators build and run berths at major ports.Major ports awarded 25 PPP projects worth ₹13,355 crore in five years to 2025; terminals at the ₹76,220 crore Vadhavan port are to be privately funded.[11][12]
Gross-cost contractsOperators own and run assets and are paid per unit of service.A national tender for 10,900 electric buses for Bengaluru, Delhi, Hyderabad, Ahmedabad and Surat, paid per kilometre (December 2025).[14]
Station redevelopmentPrivate development of railway stations and surrounding land.Indian Railways plans 15 stations under PPP, including Chennai Central and Pune.[13]

Where the openings are, sector by sector

SectorWhat is on offerWhat to know
HighwaysHAM, toll (BOT) and TOT bundles; NHAI’s FY2025-26 monetisation reached ₹28,307 crore[7]The August 2026 toll model adds a buyback if traffic exceeds design capacity in two of any three years, and compensation at 90% for crossings by FASTag pass-holders.[6]
AirportsBundled leases of Airports Authority of India airportsThe proposed bundles pair a larger airport with smaller ones: Amritsar with Kangra; Varanasi with Gaya and Kushinagar; Bhubaneswar with Hubballi; Raipur with Aurangabad; Trichy with Tirupati.[10]
PortsTerminal and berth concessionsAt Vadhavan, a ₹76,220 crore, 298 million-tonne port, terminals worth ₹37,244 crore are to be privately funded.[12]
RailwaysStation redevelopment15 stations are planned under PPP; Vijayawada was the first out to bid in 2026.[13]
Urban transportGross-cost bus contracts; metro PPP elementsThe 10,900 e-bus tender split roughly 4,500 buses for Bengaluru, 2,800 for Delhi, 2,000 for Hyderabad and 1,600 for Ahmedabad and Surat.[14]
Water and sewageHAM sewage plants; VGF-supported projectsSocial-sector projects can receive up to 60% of cost as viability gap funding.[1]

Where the pipeline is

Of the 852-project pipeline released in January 2026, roads lead the central list with 108 projects worth ₹8.76 lakh crore, followed by power (46 projects, ₹3.4 lakh crore) and railways (13 projects, ₹30,904 crore). Among states, Andhra Pradesh leads with 270 projects worth ₹1.16 lakh crore.[17]

The 2025-26 Budget also announced an Asset Monetisation Plan for 2025–30 to fund ₹10 lakh crore of new projects, ₹1.5 lakh crore of 50-year interest-free loans to states for capital spending, and a credit enhancement facility for infrastructure bonds.[15]

How PPP projects are financed

Indian PPPs are financed mainly with rupee bank debt and sponsor equity, with long-term lenders and investment trusts taking over once projects operate. The main sources of capital:

SourceRoleScale
Public capital spendingConstruction grants, HAM instalments and annuities paid by authorities₹12.2 lakh crore of central capital spending budgeted for 2026-27, including ₹3.09 lakh crore for the roads ministry[27]
NaBFIDDevelopment finance institution set up in 2021 for long-tenor infrastructure loans₹2.31 lakh crore sanctioned to 232 projects by July 2025, three-quarters of it for more than 15 years[28]
Commercial banks and NBFCsConstruction loans, typically refinanced after completionInfrastructure loan tenors of 15–30 years[27]
Infrastructure risk guarantee fundPartial credit guarantees during development and constructionProposed in the 2026-27 Budget[18][27]
InvITs and monetisationBuy operating assets, letting developers recycle capitalNHAI monetised ₹28,307 crore in FY2025-26[7]

For a foreign sponsor the practical points are that project debt is usually raised in rupees, that lenders will look closely at the Indian partner’s balance sheet during construction, and that the exit (to an InvIT, a pension fund or a strategic buyer) should be planned when the bid is priced.

How a PPP project gets to tender

  1. Preparation

    The sponsoring authority appoints transaction advisers, often funded by the IIPDF, which had approved 31 projects worth about ₹64 crore.[3]

  2. Appraisal

    Central projects above the value thresholds go to the PPPAC for appraisal before approval.[4]

  3. Viability gap funding

    Projects seeking VGF must show they can recover operating costs: all of them for social-sector projects and at least half for pilots.[2]

  4. Tender and award

    The authority runs the bid, usually in two stages (qualification and price), and signs the concession with the winning consortium’s project company.

  5. Financial close and construction

    Lenders sign up, the appointed date is declared once land and approvals are in place, and construction starts.

Risks foreign firms should price in

  • Disputes are common and slow. Arbitration claims against NHAI were reported near ₹1 trillion in March 2025, and NHAI has pushed contractors to use dispute resolution boards before arbitration.[21] Outcomes vary: in one 2026 case NHAI reported a net award in its favour after the concessionaire claimed more than ₹8,375 crore.[23]
  • Demand risk can break a concession. Hyderabad Metro Phase 1, one of India’s largest PPPs, was loss-making; in September 2025 Telangana agreed to buy out L&T’s stake for about ₹2,000 crore and take on around ₹13,000 crore of debt.[22]
  • Model choice matters. Annuity and HAM structures remove traffic or demand risk; toll and user-fee models keep it with the private partner.
  • Payment security varies by authority. Central agencies and lender-backed projects usually pay more reliably than smaller state or city bodies. Check escrow and termination terms before bidding.

Disputes: what the numbers show

About 60% of arbitral awards in cases involving public sector undertakings are challenged in court, according to a 2024 disclosure in Parliament, and the government has discussed further safeguards against arbitration claims on highway contracts.[26] For foreign firms this argues for three things: contract structures with less scope for disputes (annuity rather than toll), a seat and procedure agreed in advance, and Indian partners with a clean record with the authority concerned.

How foreign firms take part

Foreign participants usually enter Indian PPPs in one of four roles:

  • Investor, buying operating assets through TOT bundles and InvITs, or taking stakes in Indian developers.
  • Technology and operating partner, teaming with an Indian developer on HAM or design-build-operate projects where operating performance is paid for.
  • EPC or equipment supplier to the Indian concessionaire.
  • Lender or guarantor, alongside development banks and export-credit agencies.

In each role, the deciding questions are the same: the strength of the authority, the payment mechanism, the termination terms and the Indian partner. Our PPP and project development service helps you assess and bid for projects, and partner search finds the Indian developer or contractor to bid with.

A checklist before you bid

  1. Is the project bankable?

    Check whether it has passed PPPAC appraisal or a state equivalent, whether VGF is approved, and how much land is in hand.[4][2]

  2. Who carries demand risk?

    Annuity, HAM and gross-cost contracts leave it with the authority; toll and user-fee concessions leave it with you.

  3. How strong is the payer?

    Look at the authority’s payment record and whether payments are backed by escrow or a central scheme.

  4. What happens on termination?

    Read the termination payment formula for each default scenario; it decides what lenders and equity recover.

  5. How are disputes resolved?

    Check for a dispute resolution board, the arbitration seat and any limits on claims.[21]

  6. Who is your Indian partner?

    Pre-qualification usually depends on the partner’s completed works and net worth, so its record with the authority matters as much as yours.

Frequently asked questions

What is PPP in India?

A public-private partnership is a long-term contract in which a private company finances, builds or operates public infrastructure or services in return for tolls, user fees or payments from a government authority. India uses PPPs for roads, ports, airports, railway stations, water and sewage plants, urban transport and more.

What are the main PPP models in India?

BOT-Toll, the Hybrid Annuity Model (HAM), Toll-Operate-Transfer (TOT), infrastructure investment trusts (InvITs), long-term airport leases, port terminal concessions, gross-cost contracts for buses, and station redevelopment.

How big is India’s PPP pipeline?

In January 2026 the Finance Ministry published a three-year pipeline of 852 PPP projects worth more than ₹17 lakh crore, led by roads, power and railways.

What is viability gap funding?

Grant support from the central government, often matched by the state, for PPP projects that are economically justified but not commercially viable. Social-sector projects can receive up to 60% of project cost (30% central plus 30% state).

Can foreign companies invest in Indian PPP projects?

Yes. Foreign direct investment of up to 100% is allowed under the automatic route in most infrastructure sectors, and foreign investors take part as investors, operators, technology partners, EPC contractors and lenders.

Related

Sources

  1. PPP in India (DEA), VGF guidelines
  2. Department of Economic Affairs, Viability Gap Funding scheme
  3. Department of Economic Affairs, IIPDF scheme
  4. Ministry of Shipping, PPP guidelines including PPPAC notification
  5. JSA, National Monetisation Pipeline 2.0, March 2026
  6. Fox Mandal, MoRTH revises BOT-Toll model concession agreement, 2026
  7. NBM&CW, NHAI monetises assets worth ₹28,307 crore, March 2026
  8. Housing.com, concession agreement for STPs in West Bengal, June 2019
  9. Projects Today, new phase of airport privatisation, April 2025
  10. Channel IAM, 11 AAI airports proposed for PPP, August 2026
  11. Lokmat Times, 25 PPP projects by major ports, August 2025
  12. Indian Infrastructure, Vadhavan port PPP, June 2024
  13. Indian Infrastructure, 15 railway stations under PPP, August 2026
  14. Outlook Business, CESL tender for 10,900 e-buses, December 2025
  15. Construction World, Budget 2025-26 takeaways for infrastructure
  16. News on AIR, three-year PPP pipeline worth ₹17 lakh crore, January 2026
  17. ThePrint, Finance Ministry unveils 852 PPP projects, January 2026
  18. KPMG, Union Budget 2026-27 and public infrastructure, February 2026
  19. ADB PPP Monitor, India
  20. World Bank, Private Participation in Infrastructure 2023 annual report
  21. Mint, NHAI to tighten dispute resolution, June 2025
  22. The Week (PTI), Telangana to take over Hyderabad Metro from L&T, September 2025
  23. The Week, NHAI arbitration in Panipat–Jalandhar cases, May 2026
  24. Invest India, National Infrastructure Pipeline, May 2020
  25. Onmanorama, National Monetisation Pipeline 2.0, February 2026
  26. Mint, government mulls guard rails to curb arbitration against NHAI, October 2025
  27. Fox Mandal, Union Budget 2026: structural shifts in infrastructure and project finance
  28. PSU Watch, NaBFID sanctions loans worth ₹2.3 lakh crore to 232 infra projects, August 2025

Talk to a partner about India

Tell us what you make or build and where you want to be in India. A partner reads every enquiry and replies within one working day.

UBR Infra · Worli, Mumbai
info@ubrinfra.com
+91 22 2492 7671







    By submitting, you agree that we may use these details to reply to you, as set out in our privacy policy. We do not sell your details or add you to mailing lists without asking.